Resin Bound Driveway, Silver Granite Setts & Entrance Path — Carlisle

Two-tone resin held inside a hand-laid granite frame

A cracked tarmac frontage lifted out and rebuilt as two complementary resin surfaces — a warm golden path to the door and a cool silver-grey drive to the garage — separated and framed by hand-laid silver granite setts and a charcoal kerb line.

Installation film — cracked tarmac to two-tone resin frontage0:13

What the homeowners described as a simple driveway turned into a proper rebuild once the tarmac came up. The old surface had been laid thin over made ground, it was breaking at every edge, and the fall ran gently back towards the house rather than away from it. Patching would have bought a season; rebuilding buys decades.

The frontage was stripped in a morning. A mini excavator lifted the broken tarmac and the soft material underneath, and every bucketful went straight into a grab lorry standing at the kerb — no spoil heaps on the lawn, no material tracked across the pavement.

Clean stone was tipped straight from the grab into the excavation and worked out in layers, each one compacted before the next went down. Only when the base was solid did the setting out begin, and that is where the project changed character.

Rather than one uncontained surface, the drive was drawn out in stone. A charcoal kerb line was bedded on concrete along the boundary, and silver granite setts were laid by hand — bedded, tapped down, string-lined and levelled one at a time — to form the edge of the drive, the path to the front door and a crisp threshold at the step.

Two resin blends were then mixed in weighed batches: a warm golden gravel for the entrance path, and a cooler silver-grey for the main drive. Each was barrowed out onto the primed base, spread, hand-trowelled and finally power-floated to a dead-flat, seamless finish. The granite keeps the two apart and ties them together at the same time.

Service
Resin Bound Driveway, Silver Granite Setts & Entrance Path
Location
Carlisle
On site
5 working days on site
Finish
Golden path and silver-grey drive framed by hand-laid granite setts
Investment
Comparable investment: £10,500 – £14,000
Installed
July 2026
Project type
Full frontage driveway, entrance path and threshold
Size
Approximately 70m²

What we solved

The problems that decide how a driveway ages.

01

A surface that was thinner than it looked

Once the tarmac lifted it was clear the original drive had almost no base beneath it. The excavation went deeper than planned and the sub-base was built up in compacted layers — the reason the finished surface will stay flat under a car.

02

Falls that ran the wrong way

Water had been drifting back towards the front step. Levels were reset from the threshold outwards so the whole frontage now drains away from the house, with the permeable surface taking the rest.

03

Setting two surfaces against each other cleanly

A gold path meeting a silver drive only works if the junction is perfect. Granite setts were laid first as a permanent divider, then both resin blends were poured tight to the stone — no feathered edges, no colour bleed.

Installation timeline

Five days, stage by stage.

  1. Day 1

    01 — Initial site preparation

    Frontage set out and protected, the pavement crossing kept clear, and a walkable route to the front door agreed with the homeowners before anything was lifted.

  2. Day 1

    02 — Excavation

    Broken tarmac and the soft material beneath it lifted by mini excavator and loaded straight into a grab lorry at the kerb, so nothing was stockpiled on the lawn.

  3. Day 1–2

    03 — Groundworks and levels

    Formation trimmed and checked, falls reset away from the front step, and the finished level worked back from the threshold and the road.

  4. Day 2

    04 — Sub-base construction

    Clean open-graded stone tipped from the grab and spread in layers, each one compacted before the next — the part nobody sees and everything depends on.

  5. Day 2

    05 — Drainage

    Surface water directed to the kerb line, the existing chamber brought up to finished level and a recessed cover fitted ready to be infilled.

  6. Day 3

    06 — Kerb and granite sett edging

    Charcoal kerb bedded on concrete along the boundary, then silver granite setts laid one at a time to a string line, tapped down and levelled by hand.

  7. Day 3–4

    07 — Entrance path and threshold detailing

    The path to the front door framed in the same granite and the step threshold set square, so the door opens onto stone rather than onto an edge.

  8. Day 4

    08 — Surface installation

    Golden quartz and silver-grey blends mixed in weighed batches, barrowed out onto the primed base and spread tight to the granite on both sides of the junction.

  9. Day 4

    09 — Finishing details

    Each area hand-trowelled while workable, then power-floated to a dead-flat finish, with the recessed cover infilled to match the surrounding blend.

  10. Day 5

    10 — Final clean and completed transformation

    Surface left to cure, setts brushed down, the site swept clear and the frontage handed back with aftercare guidance.

  • Drive, path and threshold read as one designed frontage
  • Water falls away from the house instead of towards the step
  • Fully permeable — no joints, no weeds, no loose stone
  • Hand-laid granite frame that will outlast the surface it holds
  • Off-street parking regained without losing the front lawn

From the film

Stills from site.

Cracked tarmac driveway broken out in front of a red-brick Carlisle house
Before — thin tarmac breaking up at every edgeBefore
Mini excavator lifting broken tarmac from a front driveway
The old surface stripped in a single morningPreparation
Grab lorry bucket loading driveway spoil at the kerb
Spoil straight to the grab lorry — nothing left on the lawnPreparation
Clean sub-base stone tipped into an excavated driveway
Clean stone tipped and worked out in compacted layersGroundworks
Installer levelling a kerb block beside a front door with a spirit level
Levels reset from the threshold outwardsGroundworks
Charcoal kerb line bedded on concrete along a driveway boundary
Charcoal kerb bedded on concrete and haunchedConstruction
Installer laying silver granite setts by hand along a driveway edge
Granite setts laid one at a time, tapped down by handConstruction
Line of silver granite setts set out to a string line beside a lawn
Every sett checked against the line before it staysConstruction
Golden resin bound aggregate barrowed onto a prepared entrance path
Golden blend barrowed out to the entrance pathInstallation
Installer spreading resin bound gravel across a prepared driveway base
Spread tight to the granite — no feathered edgesInstallation
Installer hand-trowelling resin bound surface smooth
Hand-trowelled while the mix is still workableInstallation
Power float machine standing on a freshly laid resin driveway
Power-floated to a dead-flat, seamless finishFinishing
Silver-grey resin driveway being finished in front of a brick house
The silver-grey drive brought to its final levelFinishing
Golden resin path meeting granite setts at a navy front door
The door now opens onto stone, clean and dryCompleted
Completed two-tone resin driveway with granite sett edging in Carlisle
Gold to the door, silver to the garage, granite throughoutCompleted